ERCOT’s NOGRR282 has been in effect since 2026-08-01 (ERCOT NOGRR282). The Public Utility Commission of Texas approved it on 2026-07-09. It adds two sections to the Nodal Operating Guide, 2.6.4 for frequency and 2.15 for voltage (PUCT report). Ride-through here means the load stays connected and keeps drawing power through a disturbance (PUCT report, 2.6.4(5) and 2.15(3)).
Who it covers
The rule covers a Large Computational Load. ERCOT defines a Large Load as one or more facilities at a single site with aggregate peak demand of 75 MW or more. A Large Computational Load is a Large Load in which 50% or more of the demand is power electronic computational load. Data centers and cryptocurrency mining are examples (NPRR1308 report).
The exemption
A customer is exempt if it can show the load was operating, or had written ERCOT approval to energize, on or before 2025-11-14. A second route needs all interconnection or service extension agreements executed by that date. On that route, the transmission provider must also have had notice to proceed with construction and the financial security by then. Either the interconnection study must have been approved by then, or ERCOT must have approved a utility attestation and the load must energize by 2026-12-31. A later modification that meets the study trigger in Planning Guide 9.2.1 ends the exemption (PUCT report, 2.6.4(1) and (2), 2.15(1) and (2)).
What the text requires
For frequency, the load must ride through 58.8 to 61.2 Hz continuously. It must ride through 57.5 to 58.8 Hz and 61.2 to 63.0 Hz for at least 299 seconds (PUCT report, 2.6.4 Table A). Ride-through is not required while the load acts under an under-frequency load shed program or an Ancillary Service (PUCT report, 2.6.4(3)).
For voltage, the minimum ride-through times are below. The measurement point is the Service Delivery Point. Where the load shares a site with a generation or storage resource, it is the Point of Interconnection Bus (PUCT report, 2.15 Table A).
| Voltage, per unit | Minimum time |
|---|---|
| Above 1.10 to 1.20 | 1.0 s |
| 0.90 to 1.10 | Continuous |
| 0.80 to below 0.90 | 2.0 s |
| 0.50 to below 0.80 | 0.5 s |
| 0.35 to below 0.50 | 0.25 s |
| Below 0.35 | 0.15 s |
Cooling or mechanical load may trip below 0.35 per unit (PUCT report, 2.15(3)). Below 0.8 per unit the load may reduce consumption. It must return to at least 90% of its pre-disturbance consumption level from the grid within two seconds of voltage recovering above 0.90 per unit (PUCT report, 2.15(3)(c)).
What that means in the electrical room
Protection that trips or transfers the load must allow ride-through “to the maximum level the equipment allows” (PUCT report, 2.15(5)). Frequency protection shall not trip the load on an instantaneous frequency measurement (PUCT report, 2.6.4(8)). Instantaneous over-current and over-voltage protection must use filtered quantities or time delays (PUCT report, 2.15(6)).
The sag-counting rule
NERC reported a scheme that counts voltage disturbances and keeps the load on backup until someone reconnects it by hand. Three disturbances within one minute was the typical setting (NERC Incident Review, p. 7). A load that must ride through each sag shall not trip or transfer solely on a count of sags or swells in a period. Where equipment limits force such a scheme, the load must stay connected through at least six sags or swells within 90 seconds (PUCT report, 2.15(7)).
Failure, root cause and disconnection
If ERCOT finds that a load failed to ride through, the customer must report the root cause within 90 days of the ERCOT request. It must then submit a plan within 90 days and implement it within 180 days of that, unless ERCOT approves a longer timeline. If operation after the failure poses an imminent risk to local or system reliability, ERCOT may require the load to disconnect from the ERCOT System until the customer shows it can comply (PUCT report, 2.6.4(9) and 2.15(8)).
What the rule does not do
The approved NOGRR282 text names no fine or penalty (PUCT report). A separate request is NOGRR289. It would give a load whose cooling load cannot yet meet the requirements 365 days after its in-service date to comply (NOGRR289 ROS report). The ERCOT issue page lists it as pending (ERCOT NOGRR289).
What Software-Defined Electricity does at the panel
Software-Defined Electricity is a computer at the panel. It measures the current waveform and corrects it digitally, within the same cycle. It separates the working current from the reactive, harmonic and unbalanced parts, and supplies those parts from the panel, within its rating (3DFS SDE summary page).
Those currents make a small share of the voltage drop on a stiff utility service. On a generator, a long feeder or a microgrid their share is larger (3DFS voltage stability page).
How Software-Defined Electricity is the differentiator during a sag
A sag puts the site’s own load against it. A regulated supply holds its output power, so the UPS rectifier draws more current as the voltage falls. That current deepens the drop on the facility’s own impedance, so a panel sees a deeper sag than the Service Delivery Point. The protection then has less room before it trips (3DFS data centers page).
Correction removes the part of that current that does no work, so the drop the site adds to its own sag shrinks. The gap between load level and trip level widens (3DFS data centers page). In our assessment of two server racks, reactive current at the fundamental fell from 7.27 A to 0.18 A (3DFS resilience page).
The controller does not provide ride-through (3DFS standards compliance). The UPS, the static switch, the battery and the protection settings decide whether the facility stays connected (3DFS data centers page).
Critical perspective
The Texas Blockchain Council told ERCOT that a low-voltage fix costs “upwards of $1 million per MW” (Texas Blockchain Council, March 18, 2026). The estimate comes from a party that would pay it. ERCOT’s own cost is staff, at $600K to $750K a year (PUCT report).
The exemption carries the larger risk. ERCOT wrote on September 25 that many operating computational loads are exempt and “may significantly reduce consumption during normal system disturbance events”. It expects to hold consumption at identified exempt sites below each operating limit’s 3,200 MW cap in real time, counted across the exempt sites in that group (ERCOT, NOGRR289 comments). The exempt sites pay in curtailment, not in retrofit.
NOGRR289 would add cooling load to that exposure. ERCOT’s preliminary assessment assumed cooling at 20% to 30% of approved load and found more load unable to ride through in the affected areas (ERCOT). ERCOT wants any surviving cooling exemption to end no later than June 30, 2027, the earliest end date on the record (ERCOT). Google and Skybox proposed December 31, 2029 (Google and Skybox comments on NOGRR289). A developer in the ERCOT queue should not schedule around NOGRR289 relief.
Frequently asked questions
Does NOGRR282 apply to a 30 MW data center? Not as a Large Computational Load. The Large Load definition starts at 75 MW of aggregate peak demand at a site (NPRR1308 report).
Does backup power satisfy the rule? Not by itself. The text bars a move to backup solely on a sag count when the load must ride through each sag (PUCT report, 2.15(7)).
Is there a fine? The approved text states no fine. ERCOT may require disconnection when operation after a failure poses an imminent reliability risk (PUCT report, 2.15(8)(c)).
Does a power quality controller meet the rule? No. Our controller does not provide ride-through (3DFS standards compliance).