CLO-001-1, CLO-002-1 and CLO-003-1 are three NERC Reliability Standards for data centers and similar sites, adopted by NERC’s Board and awaiting FERC approval. They cover interconnection studies and modeling data (001), operating data and communications (002), and protection coordination and disturbance recording (003). Each applies to Computational Load Sites with a total load of 50 MW or more, supplied at 100 kV or more from one or more points of connection (CLO-001-1 final text). The final ballot closed on 2026-10-14, NERC’s Board adopted the computational load standards on 2026-10-26, and NERC must file with FERC by 2026-12-31 (NERC Project 2026-02, FERC order, Docket RD26-7-000). They set no industry-wide minimum voltage or frequency ride-through (NERC FAQ, October 2026). PJM expects those requirements in NERC standards in 2027 (PJM Inside Lines, 2026-08-11).
Why FERC asked for them
On 2026-07-16 FERC directed NERC to file computational load standards by 2026-12-31 and expects registry criteria by the same date. It also asked for a workplan for further standards by 2027-03-01 (FERC order). FERC cited multiple grid disturbances in which computational loads caused or contributed to instability. Six days after the order, on 2026-07-22, about 3,800 MW of load in the Dominion zone transferred to backup generation after a 230 kV line was removed from service (PJM Inside Lines). Read the full account in 3,800 MW left the grid.
What each standard requires
The summaries below follow the final ballot texts of October 2026 (NERC Project 2026-02).
CLO-001-1: interconnection, studies and modeling data
Transmission owners and distribution providers document interconnection requirements for these sites. Transmission planners and planning coordinators study new interconnections and “qualified changes,” which each planning coordinator defines. Site owners supply model data and show that the model represents the design and settings of the in-service equipment (CLO-001-1 final text). The model data covers parameters, settings and capabilities related to cessation, tripping, ride-through and post-disturbance recovery. It records what the site can do. It does not set a minimum.
CLO-002-1: operating data and communications
Transmission operators, balancing authorities and reliability coordinators specify the data they need for operations planning and real-time monitoring. Site owners and operators must supply it. The site operator must follow their Operating Instructions unless doing so is physically impossible or would violate safety, equipment, regulatory or statutory requirements. The standard also requires Interpersonal Communication capability with the balancing authority and transmission operator, and training for operators who receive oral instructions (NERC Project 2026-02).
CLO-003-1: protection coordination and disturbance monitoring
Requirement R1 calls for sequence-of-events recording on site breakers. R2 and R3 call for fault recording on the high side of the main power transformer, at a minimum of 64 samples per cycle. R4 calls for continuous dynamic disturbance recording. R2 to R4 fall on whoever owns the main power transformer, which may be the site owner, the transmission owner, the distribution provider or the generator owner. R9 and R10 require a documented process to coordinate protection settings so that devices operate in the intended sequence during faults (NERC Project 2026-02).
Who registers
The standards name two new entities, the Computational Load Owner and the Computational Load Operator, alongside existing transmission, distribution, generation, planning and operating entities. A Computational Load Site is one or more buildings, structures or installations at a single location that primarily contains information technology infrastructure (CLO-001-1 final text). NERC says the standards’ applicability aligns with the same 50 MW criterion in the proposed registry criteria (NERC FAQ). An earlier proposal of April 2026 used 20 MW at 60 kV (Texas RE summary of the NERC proposal). NERC’s Board approved the Rules of Procedure changes on 2026-10-08, separately from the standards. FERC must still approve them.
Timeline
| Date | Event | Source |
|---|---|---|
| 2026-07-16 | FERC directs NERC to file standards | FERC |
| 2026-08-19 to 09-18 | Comment period (initial ballot 09-09 to 09-18) | NERC Project 2026-02 |
| 2026-10-08 | NERC Board approves registry criteria | NERC Project 2026-02 |
| 2026-10-14 | Final ballot closes | NERC Project 2026-02 |
| 2026-10-26 | NERC Board adopts the standards | NERC One Stop Shop workbook |
| 2026-12-31 | FERC filing due | FERC |
| 2027-03-01 | Workplan for further standards due | FERC |
| 2027 | Ride-through expected in later NERC standards | PJM |
In the final ballot, approval ran from 78.13% (CLO-002-1) to 82.69% (CLO-003-1), weighted by segment (NERC Project 2026-02).
ERCOT NOGRR282 and PRC-029-2
ERCOT’s NOGRR282 sets frequency and voltage ride-through requirements for large computational loads in ERCOT. The Public Utility Commission of Texas approved it on 2026-07-09, effective 2026-08-01 (ERCOT NOGRR282). Its scope is ERCOT’s own and should not be read from the NERC 50 MW test.
PRC-029-2 is a different subject. It sets ride-through for inverter-based resources such as solar, wind and battery plants, not loads. NERC’s One Stop Shop workbook lists PRC-029-1 as inactive since 2026-09-30 and PRC-029-2 as mandatory and enforceable from 2026-10-01 (NERC). See the PRC-029 article, which carries a correction.
What happens electrically inside a facility
A site can trip on a fault that the grid clears correctly. PJM’s Operating Committee chair said of the July 22 event that “These data centers are too sensitive to the kind of voltage that they like, and we feel they are disconnecting too early” (PJM). NERC’s Large Loads white paper also reports oscillations arising from the interaction of data center UPS input units in Dominion’s system (NERC white paper, July 2025). CLO-003 R9 and R10 require the site owner to coordinate protection settings with the owners of connected grid equipment. No standard in this set says when a site may transfer to backup power. A panel-level controller is not a compliance product and does not provide ride-through. It addresses harmonic and reactive current inside the facility (3DFS).
Critical perspective
FERC called it imperative that NERC address computational loads in a timely manner (FERC order, p. 5). CLO-003-1 reaches sites already in service last. Their recorders are due 36 months after the effective date (CLO-003-1 implementation plan, p. 3). In NERC’s own example, an effective date of 2027-04-01 sets that deadline at 2030-04-01 (CLO-003-1 implementation plan, p. 3). The study duty in CLO-001-1 reaches an existing site only when it seeks a qualified change (CLO-001-1, p. 5). Each planning coordinator writes its own definition of that change (CLO-001-1, p. 6).
The recording duties in R2 to R8 fall on the owner of the main power transformer. That may be the utility, not the site (NERC consideration of comments on CLO-003-1, p. 314). Asked who pays, the drafting team called cost allocation “a commercial matter” for interconnection and service agreements (p. 305). Two Northeast reliability bodies said they could not call the standard cost effective without a cost study (p. 304, p. 354). One commenter put the cost per megawatt at a 50 MW site at roughly an order of magnitude above a 500 MW site (p. 315).
The set leaves three things to later work. NERC lists ride-through as a high priority for a separate standard authorization request (NERC FAQ, pp. 18 to 19). The standards check that a model matches the installed equipment, not that it matches measured behavior (NERC FAQ, p. 20). A white paper on that validation targets 2027 (NERC FAQ, p. 20). Registration of site owners is expected to begin in 2027 (CLO-001-1 implementation plan, p. 3).
The Dominion events came from operating data centers that disconnected from the grid (PJM Inside Lines). Sites like them get the longest schedule. An owner should not plan around 2030. The recorder bill will arrive through the interconnection agreement. Settle who installs, owns and pays for the recorders in the next agreement the utility sends.
Frequently asked questions
Do the standards require ride-through? No. NERC says they do not address industry-wide minimum voltage and frequency ride-through (NERC FAQ), and PJM expects those requirements in 2027 (PJM).
Does a 30 MW site fall under them? Not under the standards, which apply from 50 MW at 100 kV or more (CLO-001-1 final text).
Are the standards in force? No. NERC has not yet filed them with FERC. Each takes effect on the first day of the calendar quarter after FERC approval. Compliance then phases in over up to 9 months (CLO-001), 12 months (CLO-002) and up to 36 months for recorders at existing sites (CLO-003) (NERC Project 2026-02).
Is a Level 3 alert the same thing? No. NERC’s Level 3 alert of 2026-05-04 asked for essential actions and states that it is not the same as a Reliability Standard (NERC Level 3 alert, NYSRC copy).
Do multi-tenant sites register once? Not necessarily. NERC says one site can have more than one registered owner and operator, and at a multi-tenant site a shared operating function can act as the single operator for CLO-002-1 (NERC FAQ).
Related: FERC and data centers and data center and compute solutions.