A data hall trial measures what correction does on a site’s own load. It starts with one week of measurement at one PDU (3DFS data centers). That week is the baseline for the corrected readings, on the same load (3DFS Resilience).
What a trial decides
A trial decides one thing: whether the current measured at one PDU justifies a larger step. Verify released capacity and net savings at equal useful output. Where the limit is a contract in megawatts, correction adds little capacity under that limit (3DFS data centers). A trial starts by naming the limit that binds, kVA or megawatts.
The measurement week is the one duration the data centers page states (3DFS data centers). The analysis has none (3DFS Site analysis). Ask for the pilot schedule in writing before it starts.
What the first week of data shows
The week compares temperature and current. Read the sag and interruption counts against the equipment’s own curve. Read the transformer temperature and the feeder current before and after correction, on the same load. We expect the counts to stay the same and the margins to change (3DFS Resilience).
The sag count also matters for protection. NERC reviewed a July 2024 event and described a data center scheme that counts voltage disturbances on the grid. A typical setting is three disturbances in one minute. The load then transfers to the backup system and stays there until it is manually reconnected (NERC Incident Review, p. 7).
NERC attributed most of the load loss in that event to automatic reclosing on the faulted line interacting with such a scheme (NERC Incident Review, p. 8). The sag log gives the count, and the protection settings decide the response.
How to read a PQRA report
PQRA scores waveform recordings from any power quality instrument and returns a report. Access starts on a waitlist. The output has five parts (3DFS PQRA):
- a scored risk for each recording
- an economic impact layer of downtime and restart cost ranges
- links from each conclusion to its source measurements
- an equipment assessment of transformers, drives and critical loads
- a report with clear next actions
A reading order for executives:
1. Start with the grades, and rank the locations by risk. 2. Read each cost as a range, and ask which recording period it rests on. 3. Follow one conclusion’s link to its measurement. 4. Read the equipment assessment. 5. End with what to fix first.
The tests and rules beside the trial
NERC’s Level 3 alert asks transmission owners to set up a commissioning process for computational loads. Where possible, it should include a full facility load and no-load test, and at least a 10% change from nominal voltage, up and down. The computational equipment should be installed and operational for these tests (NERC Level 3 alert, p. 6). In ERCOT, NOGRR282 sets ride-through requirements for large computational loads, effective 2026-08-01 (ERCOT).
Five questions to settle before the trial starts
1. Which limit binds the site, kVA or a contract in megawatts? (3DFS data centers) 2. Which instrument records the baseline, does it log S, P and Q, and who owns the recording? 3. What is the pass number, stated at equal useful output before the trial starts? 4. How does the site’s protection count sags, and what does it do at the limit? 5. Which commissioning tests sit in the transmission owner’s process, and who schedules them?
What correction changes at the PDU
Correction supplies the reactive and harmonic share of the rack current at the panel. Where the limit is a rating in kilovolt-amperes, that rating carries more useful load. On a PDU behind the UPS, correction lightens the UPS inverter and the PDU transformer. It reaches the utility or the generator only on static bypass, maintenance bypass or eco mode (3DFS data centers).
Our 2016 assessment covered two server racks. Power factor rose from 0.931 to 0.999 on one rack and from 0.831 to 0.995 on the other (3DFS Power Factor). Total current over three phases fell from 23.8 to 22.6 amperes and from 15.9 to 13.8 amperes. The controller’s own instrumentation took the readings. The assessment supports no energy-saving claim (3DFS data centers).
A trial is also a step the site can undo. The controller connects alongside the panel, not in the power path, and power stays on during installation (3DFS Products). Removing or powering down the controller leaves the panel as installed (3DFS data centers).
How Software-Defined Electricity is the differentiator in a trial
The risk in a trial is a week that measures the average and misses the event. A rack stepping to peak is a change inside one cycle (3DFS data centers). A capacitor bank switches in seconds, and an active filter answers in milliseconds. A building meter misses the reactive, harmonic and unbalanced current inside one cycle (3DFS SDE Summary).
Software-Defined Electricity corrects the current within the same cycle (3DFS SDE Summary). The pass that corrects harmonics also corrects power factor and rebalances the phases, because the three are parts of one current. An active harmonic filter does one of those at a time. The filter reaches higher orders, and the controller responds faster (3DFS Harmonics).
In one row pair of our refrigerated container bench test, power factor went from 0.82 to 1.00. Apparent power went from 8,339 to 7,229 VA. An independently facilitated test at a 208 V mixed-load panel saw the neutral fall from 15.6 amperes to 2. We will send the capture and the method on request (3DFS SDE Summary).
A trial does not prove ride-through. The controller does not provide it (3DFS Standards Compliance). The week proves the current the site no longer carries, on its own instrument (3DFS data centers).
Critical perspective
We ship the controller, and PQRA scores the recordings (3DFS data centers, 3DFS PQRA). A third party should log the week, so the baseline is theirs and not ours (3DFS Resilience).
The Department of Energy’s data center addendum sets measurement and verification steps for a more efficient UPS (FEMP Data Center Addendum, p. 53). It recommends 15 or 30 days of measurement after installation, including changes in load, then extrapolates to a full year. The customer approves the parameters before measurement starts and witnesses the activities (FEMP Data Center Addendum, p. 54).
Run the trial on those terms. Write the parameters, the pass number at equal useful output, the witness and the third-party reviewer into the plan first. Log the baseline week, then 15 or 30 days with correction on. If needed, a third-party expert helps write the plan and reviews the reports (FEMP M&V Guidelines 5.0, p. 43).
Frequently asked questions
How long does a trial take? The measurement takes one week at one PDU (3DFS data centers). The pilot has no stated duration (3DFS Site analysis).
Can a trial prove ride-through? No. The UPS, the static switch, the battery and the protection settings decide whether the facility stays connected (3DFS data centers).
Does a data center have to answer the Level 3 alert? The registered entities NERC sent it to must acknowledge it and report their status, and NERC is working to register a Computational Load Entity for these loads (NERC Level 3 alert, p. 1). NERC says the alert is not a Reliability Standard and creates no mandatory obligation to take the Essential Actions (NERC Level 3 alert, p. 2).
Where does a trial start? It starts with the site analysis. The request form asks for voltage and phases, the installed correction equipment and the symptoms on site (3DFS Site analysis).
Related: site analysis, data center solutions, PQRA, resilience, grid rules hub.